Out of Hours Sunday day works in Gungahlin 13 May to 10 June

With on-track testing of the Light Rail Vehicles (LRVs) scheduled to begin in late May, extra working hours are required to complete necessary activities along the light rail corridor. The additional working hours are scheduled for 13 May, 20 May, 27 May, 3 June, 10 June between the hours of 7:00am to 6:00pm.

Additional Information:

The key activities that will be undertaken over the next six Sundays includes landscaping, rail welding installing in-ground services and light stop construction.

The equipment to be used includes excavators, hydrovac trucks, a plate compactor, a digger, light vehicles and trucks.

There will be NO use of heavy equipment 7:00am – 8:00am and 5:00pm -6:00pm

Due to the nature of the work, some of the activities will be noisy. The project team will limit these impacts wherever possible by reducing the number of machines operating at the same time and turning off equipment when not in use. Non-tonal reversing beepers will be used and workers will be instructed to keep noise to a minimum.

Thank you for your patience during these important works. To receive a construction update via SMS please text “YES” to 0428 446 028. This is a free service.

More Information:
If you have any questions related to works in your local area or the wider project, please contact Canberra Metro:

Facebook or Twitter Search ‘Canberra Metro’

*except for elevated work platforms which are required by safety regulations to have tonal beepers.

Publish date:
04 May 2018
View more updates in
Top