Traffic lights at the Federal Highway-Flemington Road intersection need to be re-configured with new traffic signals to accommodate Light Rail vehicles. These works will include saw cutting of concrete kerb to install new traffic light configuration.

The hours of work will be from 8:00pm to 6:00am from Sunday 1 July through to Friday 6 July.

 

Traffic Management and Detours:

There will be no change for traffic travelling northbound and southbound along Federal Highway and no change for traffic entering or exiting Flemington Road.

Lane reductions will be in place with traffic management highly visible throughout the works, including signage and personnel.

 

Additional Information:

The equipment that will be used includes a truck with on-board crane, light towers, concrete saw and light vehicles.

These works are considered low in potential noise impact. The project team will ensure the number of machines operating at the same time is limited and equipment turned off when not in use. Non-tonal reversing beepers will be used* and workers will be instructed to keep noise to a minimum. 

 

Thank you for your patience during these important works.