Extended Out of Hours Notice - Northbourne Avenue Gould-Elouera Streets Intersection, 4 - 30 July 2018

Additional time is required to complete storm water works and road asphalting within the current closure of Gould-Elouera Streets intersection. The original completion date of 27 July has now been revised to Monday 30 July. Hours of work will be from 8:00pm to 6:00am each night.

 

There will be NO night shift scheduled for Friday 13 and Saturday 14 July.

However, this extension now includes work over the two weekends starting Friday 20 July and Friday 27 July.

 

Traffic Management and Detours:
There will be no change for traffic travelling northbound and southbound along Northbourne Avenue. Traffic management will be highly visible throughout the works, including signage and personnel.


Additional Information:
The equipment that will be used includes: an excavator, tipper truckers, vacuum truck, lighting towers compaction plant and light vehicles.

The project team will ensure the number of machines operating at the same time is limited and equipment turned off when not in use. Non-tonal reversing beepers will be used* and workers will be instructed to keep noise to a minimum. 

 

Thank you for your patience during these important works.


If you have any questions related to works in your local area or the wider project, please contact Canberra Metro:

To receive a Construction Update via SMS please text “YES” to 0437 056137