Out of Hours Notice Alinga Street and Northbourne Avenue 3-6 April and 8-13 April 2018

Scope of Works:
The works are scheduled to occur from Tuesday 3rd April to Friday 6th April and again from Sunday 8th April to Friday 13th April. Hours of work will be 8:00pm to 6:00am.

UPDATE: These out-of-hours works have been extended to continue until Friday 20 April, 8:00pm - 6:00am each night, excluding Friday and Saturday night. We apologise for the inconvenience caused.

There will be one lane closed southbound on Northbourne Avenue during this time. Pedestrian and cyclist access will be maintained throughout the works. Traffic management will be in place and highly visible throughout the works, including signage and personnel.

Additional Information:
The equipment to be used includes excavators, hydrovac trucks, a plate compactor, a digger, light vehicles and trucks.  Due to the nature of the work, some of the activities will be noisy. The project team will limit these impacts wherever possible by reducing the number of machines operating at the same time and turning off equipment when not in use. Non-tonal reversing beepers will be used and workers will be instructed to keep noise to a minimum.

Thanks for your patience during these works.

 