Light Rail Vehicle Testing - Update 25 June

Summary

Light rail vehicle testing has now been underway for nearly two weeks. Currently the testing and commissioning team is running the vehicle along Flemington Road between Well Station Drive and Gungahlin Place. 

During testing, vehicle speeds are slowly increasing. With speeds of up to 20/kmh being reached on Sunday 24 June.

This week

Over the coming days, between 25 and 29 June, the testing team will continue to increase the vehicle speeds and testing the braking capabilities, whilst beginning to switch vehicles.

Publish date:
25 June 2018